DECREE NO. 243/2025/ND-CP: FURTHER SHORTENING THE TIME FOR APPRAISAL AND APPROVAL PROCEDURES OF PPP PROJECTS

DECREE NO. 243/2025/ND-CP: FURTHER SHORTENING THE TIME FOR APPRAISAL AND APPROVAL PROCEDURES OF PPP PROJECTS

2025-09-19 17:26:41 350

On March 28, 2025, the Government promulgated Decree No. 71/2025/ND-CP (“Decree 71”) amending and supplementing a number of provisions of Decree No. 35/2021/ND-CP dated March 29, 2021 (“Decree 35”) providing detailed regulations and guidance on the implementation of the Law on Investment in the form of Public–Private Partnership with many provisions facilitating enterprises, such as shortening the time for appraisal of feasibility study reports… (Clients may refer to the article here).

On September 11, 2025, the Government continued to promulgate Decree No. 243/2025/ND-CP replacing Decree 71, providing detailed regulations on a number of provisions of the Law on Investment in the form of Public–Private Partnership (“Decree 243”). Inheriting the spirit of Decree 71, Decree 243 continues to further facilitate the implementation of PPP projects.

1. Further shortening the time for appraisal and approval procedures of PPP projects

PPP projects continue to be subject to reduced time limits for implementing procedures as follows:

Type of work

Type of project

Implementation time

Decree 71/Decree 35

Decree 243

Appraisal of pre-feasibility study report

Projects under the authority of the Prime Minister to decide investment policy

Not more than 30 days

Not more than 14 days

Projects under the authority of Ministers, heads of central agencies, other agencies, provincial People’s Councils, provincial People’s Committees

Not more than 14 days

Not more than 10 days

Projects requiring expedited progress

No provision

The State Appraisal Council or the project appraisal unit shall decide the appropriate appraisal time

Appraisal of feasibility study report

Projects with an approved investment policy

Divided by approving authority, specifically:

(a) Projects under the authority of the Prime Minister: not more than 30 days;

(b) Projects under the authority of Ministers, heads of central agencies, other agencies, Chairpersons of provincial People’s Committees: not more than 14 days;

(c) Other projects: not more than 10 days

 

Not more than 10 days

Projects not subject to investment policy decision

Not more than 15 days

Projects in the public investment plan considered for conversion into PPP projects

Not more than 20 days

Projects requiring expedited progress

The project appraisal unit shall decide the appropriate appraisal time

Time for approval of PPP projects

Projects with an approved investment policy

Not more than 20 days

Not more than 03 working days

Projects not subject to investment policy decision

Not more than 15 days

Not more than 05 working days

2. Additional incentives for projects and investors that are science and technology enterprises, innovative enterprises

Decree 71 provided the following incentives: Investors with approved project proposals who are science and technology enterprises, innovative start-up enterprises; innovation centers, organizations supporting innovative start-ups in accordance with the laws on science, technology and innovation; high-tech incubators, high-tech enterprise incubators, high-tech enterprises, and enterprises newly established from investment projects producing high-tech products in accordance with the Law on High Technology shall be entitled to a 5% preferential score in the evaluation of bid dossiers.

However, investors proposing projects in the fields of science, technology, innovation, and digital transformation must provide contract performance security. The value of such contract performance security is stipulated in the bidding dossier as follows:

  • 1.5% of the total investment for projects with a total investment of up to VND 300 billion; or

  • 1% of the total investment for projects with a total investment of more than VND 300 billion.

Decree 243 takes effect from the date of its promulgation.